Maldives Transport and Contracting Company (MTCC) has stated that the development of Hdh. Nellaidhoo Harbor has made an overall progress of 83 percent.
According to MTCC, the quay wall and harbor pavement installation are now underway, with 97 percent and 96 percent completion rates, respectively.
The project includes 62,863 cubic meters of dredging and reclamation, a 331-meter breakwater, a 204-meter quay wall, a 50-meter revetment, a 2,102-square-meter paved area, navigation lights, and lighting.
The Hdh. Nellaidhoo Harbor project has an estimated value of MVR 50.8 million.