Maldives Transport and Contracting Company (MTCC) has begun work on the breakwater for the Sh. Foakaidhoo Harbor project.
According to MTCC, the construction of the Sh. Foakaidhoo Harbor breakwater started on August 15, 2021.
The project will include 39,995 cubic meters of new harbor basin dredging, 1800 cubic meters of existing harbor basin dredging, 4000 cubic meters of channel dredging, the construction of a 507-meter breakwater, a 100-meter revetment, a 464-meter quay wall, 2,320 square meters of paved area, and the installation of navigation lights and streetlights.
The Sh. Foakaidhoo Harbor development project has an estimated value of MVR 52.7 million.