Maldives Transport and Contracting Company (MTCC) has mobilized the R. Fainu shore protection project site on September 14.
The planning ministry awarded MTCC the R. Fainu shore protection project in April.
The project involves 8,100 cubic meters of sand backfilling and the building of a 250-meter geobag revetment.
The shore protection project is worth MVR 8.96 million and will take 180 days to complete.