Maldives Transport and Contracting Company (MTCC) has announced that the design and build of the R. Maduvvari South Harbor development project has proceeded by 83 percent.
According to MTCC, the installation of harbour pavement is now underway and is 60% complete.
The project will comprise dredging 7,280 cubic meters from the channel, 65,520 cubic meters from the harbor basin, a 411-meter breakwater, a 566-meter quay wall, a 135-meter revetment, a 2825-square-meter paved area, and the installation of navigation lights and streetlights.
The R. Maduvvari South Harbor development project is estimated to cost MVR 72.66 million.