Maldives Transport and Contracting Company (MTCC) has stated that the design and construction of the harbor at Bilehfahi, Shaviyani Atoll, is on schedule, with an overall project progress of 53%.
The building of the quay wall for Bilehfahi Harbor was finished on October 30th, according to MTCC, and the installation of harbour pavement is presently underway.
The project includes dredging and excavation activities totalling 24,125 cubic meters, the building of a 376-meter breakwater, a 98-meter quay wall, the installation of a 1,150sqm paved area, and the installation of lamps.
The Bilehfahi Harbor project is valued at MVR 28.42 million.