Maldives Transport and Contracting Company (MTCC) has issued an update on the harbor development project at Feydhoo, Shaviyani Atoll.
The company reported that the second shipment of granite boulders has been delivered to the project site on Tuesday.
The project includes 27,500 cubic meters of dredging and excavation, as well as the building of a 378-meter breakwater, a 90-meter revetment, and a 276-meter quay wall.
In addition, the harbor development project will include the installation of a 1,380sqm paved area, as well as the installation of lighting and navigation lights.
According to MTCC, the Feydhoo harbor development project will cost MVR 33.1 million.