Maldives Transport and Contracting Company (MTCC) has announced that the work on the Sh. Feevah Football Ground Subbase Project is approaching completion, with an overall project progress of 72 percent.
According to MTCC, drainage gutter work is now underway, with 98 percent completed.
The project entails clearing an area of 8,400 square meters, excavating a football field of 2,940 cubic meters, and backfilling a field of 4,511.70 cubic meters.
Furthermore, the project will include the supply and installation of pavement in an area of 460.29 square meters surrounding the gutter, as well as the construction of gutter and soak pit.
The Feevah Football Ground Project will cost MVR 2.68 million.