Maldives Transport and Contracting Company (MTCC) has reported the arrival of the third shipment of precast concrete blocks necessary for the building of the quay wall at the Ha. Ihavandhoo Harbor project site.
According to MTCC, the overall project work includes dredging and excavation of 30,509 cubic meters, the building of a 95-meter quay wall, a 284-meter breakwater, and a 178-meter revetment.
The project will also include the installation of navigation lights, street lights, and a paved area of 4,582 square meters.
The Ha. Ihavandhoo Harbor development project is estimated to cost MVR 59.1 million.