Maldives Transport and Contracting Company (MTCC) has reported that work on the design and construction of shore protection structures at R. Dhuvaafaru is still underway, with an overall project progress of 37 percent.
Within the same project, MTCC finished land reclamation works in R. Dhuvaafaru on August 30.
Furthermore, the project comprises 22.2 hectares of dredging and reclamation activities, as well as the building of a 423-meter rock boulder revetment and a 315-meter breakwater.
The Dhuvaafaru land reclamation and shore protection project is expected to cost MVR 143.1 million.