The Maldives Transport and Contracting Company (MTCC) has stated the harbor project in Rasmaadhoo, Raa Atoll, is nearing completion, with an overall progress rate of 75%.
According to the company, the first barge of precast concrete blocks needed for quay wall construction arrived at the project site on January 9.
Dredging and excavation operations totalling 8,100 cubic meters are part of the harbor project, as is the construction of a 377-meter breakwater.
The project will also involve the installation of 600 square meters of paved space, navigation lights, and streetlights.
The Rasmaadhoo harbor project is worth MVR 28.1 million.