Maldives Transport and Construction Company (MTCC) has announced that the second rock boulder shipment required for the Sh. Bilehfahi harbor development project was delivered to the site on August 10.
According to MTCC, the rock boulder shipment would be utilized to build a 98-meter quay wall at Sh. Bilehfahi.
The project entails dredging and excavation operations of 24,125 cubic meters; construction of a 376-meter breakwater; installation of 1,150 square meter of paved area and installation of streetlights.
The Sh. Bilehfahi Harbor project is estimated to be worth MVR 28.42 million.